Chronological Schedule of Activities
Posted December 15, 2008
2006
December 2006 – Project team assembled with OSFC as lead funding and contracting authority
2007
February 2007 through June 2007 – DeJong-Healy and Warner Concepts generated Educational Specifications and Program of Requirements (non-site specific) after a series of meetings with all user groups (teachers, youth leaders, specialists, administrators and other support service personnel)
April 02, 2007 – Interviews for Architect (selected Steed Hammond Paul Leading Designs)
April 06, 2007 – Interviews for Construction Manager (selected Bovis Lend Lease Company)
May 10 & May 11, 2007 – Team Training: Deafness 101 and Blindness 101
May 17, 2007 – First Project Core Team Meeting
June 06, 2007 – OSFC in-house partnering session
June 11, 2007 – Courtesy meeting with Bishop Watterson representatives
June 19 & June 20, 2007 – Project team tour of Virginia Schools for the Deaf and the Blind with Virginia Department of Education representatives
July 05, 2007 – Presentation to Clintonville Area Commission
July 24, 2007 – Team Partnering Session @ OSD
August 15, 2007 – Open House at OSSB
August 31, 2007 – Ohio Department of Natural Resources Arborist field walk
September 12, 2007 – State Representative Jim Hughes briefing
September 27, 2007 – OSFC presentation to Clintonville Chamber of Commerce
November 2, 2007 – Program of Requirements Completed by DeJong-Healy and Warner Concepts
November 2, 2007 – Schematic Design work started
November 27, 2007– City of Columbus traffic meeting
November 29, 2007 – Memorandum of Understanding executed (new improvements to be built on existing two campuses with understanding schools will implement operations plan that will result in annual savings of not less than $939,000.)
December 06, 2007– Franklin Soil and Water Conservation Department (FSWCD) staff and project team meeting to discuss bridge connector
December 19, 2007 – Ohio Center on Autism & Low Incidence meeting @ CM office
2008
January 11, 2008 – Team meeting with FSWCD assistant director
January 16, 2008 – Eco-Charrette at OSFC [LEED goals established]
January 25, 2008 – OSFC review with counsel from Attorney General’s office regarding bridge connector
January 28, 2008 – OSFC Communications project review with reporter
February 07, 2008 – Open House at OSD (including FSWCD representatives)
March 13, 2008 – Schematic Design 85% (non-day lighting schemes)
May 06, 2008 – Project Team meeting with Oscar Zanganeh of DAS – Office of Energy Services
May 22, 2008 – Mike Nicklas day lighting critique session no. 1
June 23, 2008 – Architects visited North Carolina schools designed by Mike Nicklas
June 18, 2008 – Team visit to Western Pennsylvania Schools for the Deaf and Blind
August 20, 2008 – Architect presentation to staff of both schools
September 10, 2008 – Mike Nicklas day lighting critique session no. 2
October 08, 2008 – Architect visited Furman University, South Carolina to view “chilled beam” installation
October 10, 2008 – Team walk of conservation easement, review proposed roadway alignment
November 13, 2008 – Team Partnering Session @ OSSB
November 24, 2008 – Schematic Design completed and signed by OSFC – OSD – OSSB representatives (featuring day lighting & chilled beam solutions)
November 25, 2008 – Design Development work started
December 15, 2008 – OSD user group to examine furniture layouts with the architects
December 16, 2008 – OSSB user group to examine furniture layouts with the architects
December 18, 2008 – Specified user groups to examine technology, phones, and security layouts with the architects
2009
January 15, 2009 – Biddings for abatement and demolition work on existing dormitories at both schools to commence in order to accommodate new construction
March 28, 2009 – Design Development work to be completed
March 28, 2009 – Early site work design project completed
APRIL 16, 2009 – Ground Breaking Ceremonies to take place (projected)
April 15, 2009 – Demolition and Abatement work on existing dormitories to be completed. (Abatement will be 5 weeks and Demolition will be immediately afterwards)
May 31, 2009 – Project bids for early site work construction bids to be awarded
June 2009 – Begin early site work construction
July 30, 2009 – Construction Documents to be completed and advertised
September 30, 2009 – Project bids for new schools and dormitories construction to be let
October 31, 2009 – Early site work construction project completed
October 2009 – Begin construction of new academic buildings and residential units
October 2009 – Begin construction of bridge connector
2010
February 2010 – Complete bridge connector
July 2010 – Complete residential units
December 31, 2010 – Construction of new schools and dormitories project completed
2011
March 2011 – Contractor’s close-out of the new schools project activities
New School Timeline for OSD
EARLY SITE PACKAGE
February 21, 2010 – First Advertisement to bid in The Columbus Dispatch
February 28, 2010 – Second Advertisement to bid in The Columbus Dispatch
March 3, 2010 – Pre-Bid meeting
March 5, 2010 – Last Addendum to be issued
March 11, 2010 – Early Site bids opened up
March 16, 2010 – 48 Hour withdraw period for bidders
March 17, 2010 – Bidder interviews
March 23, 2010 – 5 day period for OSFC to review recommended contractors
April 9, 2010 – Issue Notice to Proceed
April 16, 2010 – Contractor mobilization
MAIN BUILDING PACKAGES
February 8, 2010 – 98% CD documents ready for bid
March 22, 2010 – Construction Management Estimates, Scopes, Alternates, Final front end documents
April 8, 2010 – Complete OSFC review and Phase submission sign-off
April 11, 2010 – 1st Advertisement to bid in The Columbus Dispatch
April 18, 2010 – 2nd Advertisement to bid in The Columbus Dispatch
April 25, 2010 – 3rd Advertisement to bid in The Columbus Dispatch
April 27, 2010 – Pre-Bid meeting
May 4, 2010 – Last Addendum to be issued
May 7, 2010 – Main Building bids opened up
May 12, 2010 – 48 Hour withdrawal period for bidders, Owners determine Alternate selection based off of bids received
May 19, 2010 – Complete Bidder interviews
May 31, 2010 – Complete contractor background check & references and make recommendations
June 4, 2010 – 5 day period for OSFC to review recommended contractors
June 7, 2010 – Issue Notice of intent
June 21, 2010 – Issue Notice to Proceed
June 28, 2010 – Contractor Mobilization
|